NEC Wire Ampacity Reference (Table 310.16)
Last updated May 24, 2026
NEC Wire Ampacity Reference (Table 310.16)
NEC Table 310.16 is the go-to reference for allowable ampacities of insulated conductors not more than three current-carrying conductors in a raceway, cable, or earth. The values below are for copper conductors at 75 degrees C insulation rating, which is the standard for most residential and commercial installations.
Copper Conductor Ampacity (75 degrees C, up to 3 conductors)
| Wire Gauge (AWG) | Ampacity (75C) | Common Use |
|---|---|---|
| 14 AWG | 20A | Lighting circuits, general outlets |
| 12 AWG | 25A | General outlets, small appliances |
| 10 AWG | 35A | Dryers, water heaters (small) |
| 8 AWG | 50A | Electric ranges, dryers |
| 6 AWG | 65A | Sub-panels, AC units |
| 4 AWG | 85A | Sub-panels, large AC units |
| 3 AWG | 100A | Service entrance (small), sub-panels |
| 2 AWG | 115A | Service entrance, large sub-panels |
| 1 AWG | 130A | Service entrance |
| 1/0 AWG | 150A | Service entrance, feeders |
| 2/0 AWG | 175A | Service entrance |
| 3/0 AWG | 200A | Service entrance (200A service) |
| 4/0 AWG | 230A | Large service entrance |
| 250 kcmil | 255A | Commercial feeders |
| 300 kcmil | 285A | Commercial feeders |
| 400 kcmil | 335A | Commercial feeders |
Key Rules to Remember
80% Rule for Continuous Loads: NEC 210.20(A) requires that branch circuit conductors have ampacity not less than 125% of the continuous load plus 100% of non-continuous load. In practice, if you have a continuous load, multiply it by 1.25 before looking up the wire size.
Aluminum Derating: Aluminum conductors have lower ampacity than copper of the same gauge. For aluminum at 75C, subtract roughly 20-25% from the copper values, or go up 2 wire sizes (e.g., use 2/0 aluminum where 1 AWG copper would work).
Conduit Fill: These values assume no more than three current-carrying conductors. If you have more, apply the adjustment factors in NEC Table 310.15(C)(1).
Reference
NEC Table 310.16, 2023 edition. Always verify with your local adopted code version and having a licensed electrician review your work.